Special Courts for Trial and Disposal of Commercial Disputes, Andhra Pradesh Case No : COP - 106/2024 Diary No : 3653605002132024 M/s Sree Vishnu Constructions. VS M/s Infosys Technologies Limited Listing Date : 12/11/2024 |
||||
|---|---|---|---|---|
Hearing Details |
||||
| Date | 12/11/2024 | Court No. | 1 | |
| Proceedings Summery | Order pronounced in the open court (VSO). In the result, the petition is allowed and mandate of the learned Arbitral Tribunal comprising of Sri G. Gopala Krishna Murthy (Retd. District Judge) is extended for a period of four months from the date of this order, in pursuance to Section 29-A of the Arbitration and Conciliation Act, 1996 for completion of the Arbitral proceedings and for publishing the award in respect of the dispute between the parties. | Stage Of Case | For Order | |